Option to lock down and only able to save files in ProjectWise

Lock down to only have the ability to save files in ProjectWise will give organizations better control of files being properly stored and available to other users
15 days ago in Water Distribution Products / HAMMER 0 Needs review

Option to lock down and only able to save files in ProjectWise

Lock down to only have the ability to save files in ProjectWise will give organizations better control of files being properly stored and available to other users
15 days ago in OpenFlows FLOOD 0 Needs review

Selecting Feature Level on application startup

It is not easy or intuitive for users to select the correct Feature Level based on their expected use of the software and we are concerned that the wrong daily use gets charged
about 1 month ago in Water Distribution Products / HAMMER 0 Needs review

Add Check Valve transient results to EXTENDED NODE DATA

Transient results for surge tanks, air valves, and pumps can be graphed and viewed under EXTENDED NODE DATA tab. Please add data for check valves (flow through, pressure difference, % closed) as well to this tab.
about 1 month ago in Water Distribution Products / HAMMER 0 Needs review

Add "Copy" button to surge profile graph in Hammer

The TIME SERIES and EXTENDED NOTE DATA tabs have "Copy" buttons for graphs displayed. However, the PROFILE tab does not have this option, and the user needs to take a screenshot of the profile manually. Please add this capability to PROFILE graphs.
about 1 month ago in Water Distribution Products / HAMMER 0 Needs review

Perform computations using hydrograph peak flows

Allow for hydraulic computations to use the peak flow from hydrographs and instead of the dynamic flows generated from the hydrographs. The software StormShed (which is an allowed software for design use by WSDOT) calculates the peak flow from the...
9 months ago in OpenFlows FLOOD 1 Needs review

Bentley HAMMER batch compute option to run scenarios concurrently rather than consecutively

Hi Bentley Team, HAMMER currently runs batch computed scenarios sequentially. For complex models with multiple scenarios this often results in computations running overnight or even over several days to complete a batch of several scenarios. If po...
over 2 years ago in Water Distribution Products / HAMMER 3 Future consideration

HAMMER: Transient Results Viewer\Extended Node Data\Hydropneumatic Tank: the pressure or head engineering units indicated as absolute values on the Y axis. Without such mention a gauge value is assumed.

A new user looking for the first time at a pressure or head graph might be fooled by the fact that the Y axis does not mention that the units being graphed are in an absolute value. He or she might think hey I'm ok, minimum gauge value is 10 meter...
about 2 years ago in Water Distribution Products / HAMMER 1 Planned

REGARDING WATER LEVEL VARIATION IN HYDRONEUMTIC TANK

SIR I HAVE SEEN THAT TRACKING OF WATER LEVEL OSCILLATION HAS NOT BEEN INCORPORATED IN HAMMER. INSTEAD GAS VOLUME VARIATION IS AVAILABLE. BUT IF OUR EXPERTS CAN IMPLEMENT THE WATER LEVEL VARIATION, IT IS SO HELPFUL.
8 months ago in Water Distribution Products / HAMMER 1 Already exists

turbine load acceptance followed by load rejection

sir the above case is so important in case of surge protection of tail race tunnel and head race tunnel. Also, now a days most of the hydropower plants, the surge tank has been replaced with SURGE GALLERY (IT IS JUST LIKE LONG PIPE OF HAVING DIFFR...